|
|
Safety on Arizona SR 83 60,000 truck trips every year, over 1.2 Million trips over the life of the mine. On March 19th, 2011 recently appointed Coronado Forest Supervisor Jim Upchurch and key members of the forest service spent a day touring the Sonoita region. The tour and presentations were arranged by the Mountain Empire Action Alliance. It was a pleasant day with many excellent presentations, lots of good food, and an informative but good time had by all. We would like to welcome Jim to the Tucson area, and to thank Jim and his staff for taking a day out of their busy schedules to spend with us. Following is the presentation on Highway 83 outlining our concerns with Rosemonts proposed use of Scenic Route 83 for all of their traffic, effectively turning it into their haul road, one shared by the public.
PART 1 PART 2 We who live in the Hilton Ranch Rd community are very aware of the hazards on SR83, we have seen many accidents over the years and have seen many of the victims airlifted to the hospitals in Tucson. The typical traffic consists of residents, school buses (15 per day), motorcyclists, bicyclists, and other tourists. In addition SR83 is currently used to route oversized loads from I-10 that are unable to pass under the Marsh Station railroad bridge. The Arizona Department of Transportation mentioned this problem and suggested fixing I-10 to eliminate these oversized loads and reduce truck traffic on the scenic highway. Unfortunately this has still not been completed, but we have been informed that it will be completed in 2011. This will reduce the oversized loads traveling on SR83 and is a welcome improvement. It will improve SR83 safety, but will do nothing to change the fact that SR83 is a narrow 2 lane highway with many curves and hills, few shoulders, and many guardrails. Following are some video's to validate our concerns. During the public scoping process I expressed my concern with their plan to us SR83 for all of their mine traffic. Rosemont representatives informed me that if they could, they would like to put in a 4 lane highway and they would make sure the roadway was safe.
Copper concentrate, 56 loads per day, 7 days per week. The plant can load about four concentrate trucks per hour which will require 14 hours per day to load and ship the concentrates Sulphuric Acid Trucks 3 per hour, 9 per day, delivered during day Pebble lime trucks 5 per day, day and evening around busy times SAG and Ball mill grinding balls 4 per day 5 days week (17 total), during the day, 2 mid morning, two mid afternoon Diesel fuel, 4 per day during day between shift changes Copper Cathode, 4 loads per day, 5 days per week Ammonium Nitrate, 4 loads per day, 5 days per week miscellaneous agents, 2 loads per day 5 days per week Total of 88 Truck loads per day or 176 truck trips per day during weekdays Total of 224 concentrate truck trips per weekend
Tetra Tech prepared the AZ-83 roadway assessment report, July 2009 for Rosemont . I have read through the report and have summarized my findings: Following is a summary of the report titled “AZ-83 Rosemont Assessment” prepared for Rosemont Copper by Tetra Tech and released in July 2009. Any comments are welcome. The AZ-83 Rosemont Assessment report consists of an Executive summary, an introduction describing the Rosemont mine project, a section concerning current AZ-83 roadway assessment, a section analyzing and comparing accident occurrences on AZ-83 and AZ-77, and a section outlining potential roadway improvements. According to the Executive summary “The proposed Primary Access Road leading to the Rosemont Project off AZ-83 is located at MP 46.9. This location shows relatively low accident frequency and rate”. The report fails to mention that the sixth most accident-prone location is at MP 47, one tenth of a mile from Rosemont’s proposed primary access road. The top five (5) accident-prone locations are located at “Mile Post (MP) 44, 45, 46, 55, and 58. In particular, the roadway segment between MP 44.5 to 44.0 has the highest accident frequency for all fatal accidents along AZ-83. Additionally, locations where substandard designs are present coincide with the high accident frequency locations”. When I analyzed the ADOT accident statistics from 3/01/2002 to 2/28/2007 almost 2 years ago I found 10 accidents reported at MP 47. Tetra Tech only reports 7 accidents from 2003 to 2008. Either 3 accidents occurred from 3/1/2002 to 12/31/2002, or a mistake was made. If the 3 accidents had been included then MP 47 would be tied with MP 58 for the 4th most accident-prone location. The only significant changes proposed for the substandard, accident-prone locations are changes to AZ-83 at MP 44 where the majority of accidents occur. Several substandard
elements were identified in section 2 “Roadway assessment”.
They include: 1. Tight reverse horizontal curves are identified in Table 2.1 of the report. 1.1.
At Hilton Ranch Rd, AZ-83 intersection (MP 49.1), a
substandard horizontal curve exists. Section
2.2.3.2
states “Near the Hilton Ranch Road and AZ-83 intersection, the combination
of a hill and a horizontal curve contribute to a substandard sight distance
at this location. The alignment in the vicinity of Hilton Ranch Road is also
a concern because the intersection is on blind curve, which makes southbound
left turn movements from AZ-83 onto Hilton Ranch Road difficult. Based on the
curve data in Table 2.2, this area also has a substandard horizontal curve
alignment. Therefore, the fairly sharp curve, coupled with a steep slope,
heavy vegetation, and no shoulder, contributes to the poor sight distance at
this intersection. Finally, the roadway pavement ends less than one (1) foot
beyond the white edge stripe causing shoulder deterioration.”
No improvements are suggested to mitigate these problems beyond a
potential shoulder improvement and by adding a bus pull-off area on this
dangerous blind curve and intersection. 1.2.
At MP 47.7, 47.6, and 47.5 tight reverse horizontal curves.
MP 47 is the 6th highest accident location according to the
report using data from 2003 to 2008 provided by the ADOT.
No improvements are suggested to mitigate this problem in the report. 1.3. At MP 44.1, 44.2, 44.3 tight reverse horizontal curves. ADOT is addressing this as part of the ADOT Safety Project, “the horizontal curves within this roadway segment will be realigned, fixing the substandard curve radii. The project will also replace the existing substandard guardrails, widen the roadway shoulders, flatten the road cuts, and install new signs and striping. These improvements will increase the motorist sight distance and the overall safety of this roadway segment. This safety project is identified as Tracs number H705701C and ADOT project number 083-A(200)A. As of April 14, 2009, the project was still waiting for environmental clearance”. This work has been completed. The construction was paid for by HES funds (federal safety funds) 2.
Improper
guardrail placement Section
2.5 states “Most of guardrails
along AZ-83 fail to meet ADOT design standards since they are outdated and
located too close to the edge of the paved roadway”. According to the report
these guardrails are reported present throughout the AZ-83 study area between MP
33 and 52. However, the
illustration 2.12 shows an example of a typical substandard guardrail at the
Sahaurita Rd intersection (MP 55, substandard guardrails are present in areas
other than between MP 33 and 52).
No improvements are identified to mitigate this problem in the report.
Section 4.0 of the report states that “all potential roadway
improvements were designed not to affect existing utilities or guardrails”.
Without proper guardrail placement roadway shoulder’s
cannot be widened. 3.
Insufficient roadway shoulder widths.
Section 2.6 states the shoulders
along AZ-83 are cracked and at most locations the width is less than the
standard required 6-foot width. Section
4.6 suggests that “one of the planned ADOT projects highlighted in Section
2.6 focuses on upgrading shoulders to the required standards”. 3.1. The
only reference to an ADOT project to widen AZ-83 shoulders is mentioned in the
AZ-83 MP 44 to 45.5 Safety project which states “The project will also
replace the existing substandard guardrails, widen the roadway shoulders,
flatten the road cuts, and install new signs and striping”.
I checked ADOT’s website and find no reference to a project on AZ-83 to
widen the shoulders. The
report would imply that ADOT has plans to fix the shoulders along AZ 83, not
just a 1.5 mile stretch of them. It
is not clear if Rosemont is proposing to improve the roadway shoulders that are
not being improved by the ADOT plan. 4.
Insufficient sight distance.
The stopping sight
distance for horizontal curves is evaluated by examining the potential
obstructions along the inside region of a curve.
These are the problem areas identified in the report. 4.1.
The AZ-83 and
Hilton Ranch Rd intersection was found to be unsafe.
“Near the Hilton Ranch Road and AZ-83
intersection, the combination of a hill and a horizontal curve contribute to a substandard
sight distance at this location. The alignment in the vicinity of Hilton
Ranch Road is also a concern because the intersection is on blind curve, which
makes southbound left turn movements from AZ-83 onto Hilton Ranch Road difficult.”
No improvements are suggested to mitigate these problems beyond a potential
shoulder improvement accomplished by adding a bus pull-off area on this
dangerous blind curve and intersection. 4.2.
“A tight
horizontal reverse curve (Illustration 2.7), combined with a 6% downgrade,
deteriorates the sight distance along AZ-83 between MP 44 and 46. Moreover, the
steep road cuts within this area also obstruct the sight distance along the
horizontal curves”. The
AZ-83 MP 44 to 45.5 Safety project does not identify increased sight distance as
a result of the improvement 5.
Lack of existing School bus stops The
report identified seven existing bus stops. “With
the exception of the Hilton Ranch Road school bus stop, the bus stops do not
have a pull-off area along AZ-83 (i.e., the buses stop within the through lane
of AZ-83). At the Hilton Ranch Road school bus stop, a wide compacted dirt area
was observed on the east side of AZ-83”. The report recommends seven school bus stop pull off areas be
constructed at the current bus stop locations to improve traffic flow. The
recommended bus stop at Hilton Ranch Rd directly follows a substandard curve
with limited sight distance. The
bus will be susceptible to rear end collisions if NB traffic travels into the
pull off area for any reason. 6.
Lack of existing wide load truck turnouts Currently
no truck turnouts exist on AZ-83. Two
wide load truck turnouts are suggested.
One proposed just south of the Sahaurita/AZ-83 intersection on the west side
of AZ-83 (SB traffic side). Another is proposed at MP 47.2 just north of the
proposed primary access road. The
AZ-83 Accident analysis summary in Section 3.7 of the report states “the
major causes of accidents on AZ-83 are speeding along with the curvy roadway
geometry. Additionally, the narrow roadway shoulder and lack of adequate pull
off locations along AZ-83 adds to the safety issues since it prevents slow
moving vehicles from pulling over and allowing cars to pass. The narrow shoulder
and lack of pullouts are also safety concerns for tourists who want to enjoy the
scenic views along AZ-83”. After assessing AZ-83 for substandard design issues the following locations/issues are left unmitigated:
Tetra Tech prepared another report for Rosemont in April of 2009 the Traffic Analysis Report. The report suggests two scenarios for the operational phase. Scenario one suggests that 100% of the mine employees would participate in carpools, 5 persons per vanload. Scenario two suggests that 75% of the mine employees would participate in carpools. They also suggest that during the construction phase 100% of the 900 construction employees will arrive by bus. How convenient to avoid any form of impact on SR-83 by eliminating employee traffic. What impact would mine traffic have on SR-83 if nobody carpooled? ADOT had them complete traffic analysis without allowing for car-pooling (a more realistic scenario). Over 50% of the traffic travelling SR83 will be directly related to the mine. 60,000 truck trips every year, over 1.2 Million trips over the life of the mine. In May of 2009 Tetra Tech completed the State Route 83 Scenic Road Evaluation report for Rosemont. They claim the mine will have little impact the scenic designation or value of AZ83. If you believe that I've got a bridge for sale!
|
‘All that is necessary for the triumph of evil is that good men do nothing’ If you have information you would like to be included on this web page E-mail hiltonroad@msn.com Let us know if you would like to receive information from us
|